Portfolio
 
 

Metea Valley High School
Indian Prairie School District #204

Superintendent: Joe Barry
Updated on: 05-20-09

R.C. Wegman Construction Company is the general trades contractor for Metea Valley High School.

  • Our carpenters have begun installing doors and hardware throughout the building.  The school has over 700 doors and installation is scheduled for an August 1st completion.  Stauber Hardware has supplied all of the doors, frames and hardware to RC Wegman.  In addition installation has begun in earnest on the hundreds of markerboards, toilet accessories, and fire extinguishers.
  • Carpentry at the outbuildings is 90% complete.  The only remaining work to complete is installation of the exterior siding.
  • Our subcontractors continue to make significant progress as well.  Carroll Seating has completed the athletic equipment in the main gym.  Baum Sign is done installing all of the interior and exterior scoreboards.  Thyssen Krupp is over 
    50% completed with the elevator installation.  And Door Systems is rapidly nearing completion of all overhead and security door requirements.
 



Archived Images:
5-20-09
3-19-09
12-01-08




Archived Images:
5-27-09
5-15-09
4-9-09
4-6-09
3-18-09
3-18-09

 

FVPD Spring Lake Park

Superintendent: Rob Cinto
Updated On: 5-27-09

  • All coffer dam work at the boat ramp and fishing pier has been completed.
  • The concrete piers and the structural steel framing at the fishing pier are complete. 
  • Excavation and concrete work has been completed at the Pavilion and Restroom Buildings. 
  • Excavation and concrete work has begun at the playground area. The focus of the excavation has now turned to the parking lots. 
  • Significant portions of the landscaping have begun as well.  The 2.7 acre turf improvement portion of the work has been completed.

Oswego Central Station Headquarters
Oswego, Illinois

Superintendent: Mike Testa
Updated on: 5-20-09

Oswego’s current headquarters is over 30 years old and is outdated. The new 44,000 SF central fire station will have 15 bunks, 8 apparatus bays, 1 maintenance bay, and 6 small vehicle bays. Aesthetically, the village wanted to incorporate elements of an old Chicago fire house into the new station. The old Chicago Style architecture included in the design is complete with a bell tower and traditional red overhead doors. Traditional design was incorporated into the interior as well with the fire commander’s platform and sliding poles. The project will be completed in 2009 for an estimated cost of $10.8 Million.

 


Archived Images:
5-20-09-3
5-20-09-2
5-20-09-1
5-7-09
4-15-09-2
4-15-09-1
3-30-09-2
3-30-09-2
3-30-09-1
3-11-09
6-30-08
Ground Breaking



Archived Images:
5-20-09


 

Naperville Fire Station #10

Superintendent: Dan Peterson
Updated on: 3-18-09

  • This 10,000 square foot satellite facility serves the evolving needs of the Naperville Fire Department.
  • The design includes three drive through apparatus bays, sleeping quarters, fitness room, kitchen/eating area and living area for up to (10) personal.
  • The intent of the City of Naperville is to construct the Fire Station and obtain a LEED Silver certification.

Montgomery Fire Headquarters Addition
Montgomery, Illinois

Superintendent: Mark Werrline
Updated on: 5-7-09

  • Montgomery Fire Protection District awarded R.C. Wegman with its 7,700 square feet addition. It includes a 5 bay addition as well as converting the existing station into medic response bays with support services. A mezzanine has a large training room and the stairwell will be designed for an area of rescue exercises.

 




Archived Images:
5-20-09
5-7-09
4-15-09-2
4-15-09-1
3-19-09





Archived Images:
3-20-09
GrandOpening6
GrandOpening5
GrandOpening4
GrandOpening3
GrandOpening2
GrandOpening1

3-18-09/1

3-18-09/2
3-18Luncheon
12-01-08
9-1-08
8-20-08
8-1-08/1
8-1-08
6-26-08/1
6-26-08
6-20-08/1
6-20-08
5-13-08
5-13-08/1

5-13precast-2
5-13precast-1
2-15-08
9-6-07

 

New Aurora Police Station
Parking Garage & TAS [Training & Support] Building
Aurora, Illinois

Superintendent: Dan Peterson
Superintendent: Mike Beebe
Project Manager: Bill Arnolde
Updated on: 3-18-09

The project is completed.

This is a building that Aurora can be proud of! The new TAS [Training and Support Building] Features state of the art forensic labs, a 10 lane indoor firing range, vehical exam room, and a significant improvement of space for evidence lock-up.R.C. Wegman also completed the two story Staff Parking Garage.

The Aurora Police Station has a LEED Gold rating targeted. It is the first LEED Public project in Aurora. R.C. Wegman is proud of the site specific OSHA Partnership Agreement and site specific Project Labor Agreement with the unions trade counsel utilized on the project.


 

 

 


 

 

 


 

 



 

 