Home About Us Portfolio Contact Us Bid Calendar
 
 
Portfolio
 
 

Metea Valley High School
Indian Prairie School District #204

Superintendent: Joe Barry
Updated on: 07-20-09

R.C. Wegman Construction Company is the general trades contractor for Metea Valley High School.

  • Phase 1 of door, frame, and Hardware installation is nearing completion.The school has over 700 doors and installation is scheduled for an August 1st completion.  Stauber Hardware has supplied all of the doors, frames and hardware to RC Wegman.  In addition installation on the hundreds of markerboards, toilet accessories, and fire extinguishers are also nearing completion.
  • Carpentry at the outbuildings is complete. 
  • Our subcontractors continue to make significant progress.  Carroll Seating has completed the athletic equipment installations.  Baum Sign is done installing all of the interior and exterior scoreboards.And Door Systems is rapidly nearing completion of all overhead and security door requirements.
 



Archived Images:
7-15-09
5-20-09
3-19-09
12-01-08



Archived Images:
10.2 to 10.9-2009
9.16 to 9.29-2009
9.2 to 9.16-2009
8.29 to 9.2-2009
8.20 to 8.25-2009
8.13 to 8.19-2009
7-15-2
7-15-09-1
Groundbreaking2
Groundbreaking1
6-4-09
5-20-09

 

Naperville Fire Station #10

Superintendent: Dan Peterson
Updated on: 3-18-09

  • This 10,000 square foot satellite facility serves the evolving needs of the Naperville Fire Department.
  • The design includes three drive through apparatus bays, sleeping quarters, fitness room, kitchen/eating area and living area for up to (10) personal.
  • The intent of the City of Naperville is to construct the Fire Station and obtain a LEED Silver certification.

Hoover Forest Preserve Improvements

Superintendent: Tim Werrline
Updated on: 10-19-09

Education Building:
  • Window installation is complete.
  • Siding continues.
  • Painting has started and continues.
  • Mechanicals continue.
Rice Building:
  • Window and siding installation continue.
  • Hardwood floors are in the process of being refinished.
  • Millwork is complete. 
  • Tile work is complete.
  • Mechanical work is ongoing.
Camp Clusters:
  • Roof, siding continues.
  • Tile continues
  • Mechanicals are ongoing.

Miscellaneous

Monument sign - Has been installed

Watermian - is complete

 

Education Building

9-17-09
10-2-09
10-15-09
11-24-09
11-30-09_1
11-30-09_2
11-30-09_3
12-08-09
12-11-09
12-18-09
12-29-09
1-5-10


Camp Clusters

9-17-09_1
9-17-09_2
10-15-09
11-17-09
11-30-09_1
11-30-09_2
12-08-09
12-17-09
12-29-09

Rice Hall
9-17-09
10-1-09
10-8-09
10-15-09
11-30-09_1
11-30-09_2
11-30-09_3
12-08-09

12-11-09
12-18-09
12-29-09
1-5-10


Misc


9-17-09
10-13-09

10-15-09
11-24-09


 



Archived Images:
1-22-10
10-22-09_1
10-22-09_2

Fairview Dental Renovation

Superintendent: Mark Werrline
Updated on: 10-28-09

The project is completed.

  • Fairview is a 16 operatory 6500 sq foot facility with 4 doctors and employs (16 ) hygienists and (40 ) support staff and management.
  • The facility was kept open the duration of remodeling.
  • The business office, reception, and financial arrangements areas had cabinets, flooring, painting and wall coverings demolished and replaced over the weekends.
  • The remodeled areas where completed and turned back over to staff for full use on the following Monday.
  • On average, 850 patients per week or 3,400 per month were treated while we worked.
  • New toilets, sinks, fixtures in bathrooms

City of Aurora Communications Tower

Superintendent: Rob Cinto
Updated on: 10-28-09

  • The project is wrapping up
  • Miscelanous Electrical needs to be finished
  • Sidewalks and pavement work are left to be done on the site
 



Archived Images:
10-27-09


 

   

 



Archived Images:
Ground Breaking
11-30-09_1
11-30-09_2

Hessed House

Superintendent: Mike Beebe
Updated on: 12-7-09

  • Site work is completed.
  • Exterior facade work is completed.
  • Concrete slab work is completed.
  • Interior framing is completed.
  • Mechanical, plumbing and electrical rough-ins are nearly completed.
  • Barrel vault ceiling has been drywalled.
  • Barrel vault beams have been stained and varnished.

 

 

 


 




Archived Images:
8-24-09-1
6-4-09-2
6-4-09-1
5-27-09
5-15-09
4-9-09
4-6-09
3-18-09
3-18-09

FVPD Spring Lake Park

Superintendent: Rob Cinto
Updated On: 07-20-09

The project is completed.

  • The new park contains a fishing pier and new boat launch
  • There is a new pavilion and restrooms
  • There are new parking lots
  • Sea-scape themed playground equipment
  • Rain gardens decorate the perimeter of the park


Archived Images:
7-15-09
6-4-09-2
6-4-09-1
5-20-09-3
5-20-09-2
5-20-09-1
5-7-09
4-15-09-2
4-15-09-1
3-30-09-2
3-30-09-2
3-30-09-1
3-11-09
6-30-08
Ground Breaking

Oswego Central Station Headquarters
Oswego, Illinois

Superintendent: Mike Testa
Updated on: 5-20-09

Oswego’s current headquarters is over 30 years old and is outdated. The new 44,000 SF central fire station will have 15 bunks, 8 apparatus bays, 1 maintenance bay, and 6 small vehicle bays. Aesthetically, the village wanted to incorporate elements of an old Chicago fire house into the new station. The old Chicago Style architecture included in the design is complete with a bell tower and traditional red overhead doors. Traditional design was incorporated into the interior as well with the fire commander’s platform and sliding poles. The project will be completed in 2009 for an estimated cost of $10.8 Million.


Montgomery Fire Headquarters Addition
Montgomery, Illinois

Superintendent: Mark Werrline
Updated on: 7-19-09

The project is completed.

  • Montgomery Fire Protection District awarded R.C. Wegman with its 7,700 square feet addition. It includes a 5 bay addition as well as converting the existing station into medic response bays with support services. A mezzanine has a large training room and the stairwell will be designed for an area of rescue exercises.

 




Archived Images:
5-20-09
5-7-09
4-15-09-2
4-15-09-1
3-19-09





Archived Images:
3-20-09
GrandOpening6
GrandOpening5
GrandOpening4
GrandOpening3
GrandOpening2
GrandOpening1

3-18-09/1

3-18-09/2
3-18Luncheon
12-01-08
9-1-08
8-20-08
8-1-08/1
8-1-08
6-26-08/1
6-26-08
6-20-08/1
6-20-08
5-13-08
5-13-08/1

5-13precast-2
5-13precast-1
2-15-08
9-6-07

 

New Aurora Police Station
Parking Garage & TAS [Training & Support] Building
Aurora, Illinois

Superintendent: Dan Peterson
Superintendent: Mike Beebe
Project Manager: Bill Arnolde
Updated on: 3-18-09

The project is completed.

This is a building that Aurora can be proud of! The new TAS [Training and Support Building] Features state of the art forensic labs, a 10 lane indoor firing range, vehicle exam room, and a significant improvement of space for evidence lock-up.R.C. Wegman also completed the two story Staff Parking Garage.

The Aurora Police Station has a LEED Gold rating targeted. It is the first LEED Public project in Aurora. R.C. Wegman is proud of the site specific OSHA Partnership Agreement and site specific Project Labor Agreement with the Unions Trade Council utilized on the project.


 

 

 


 

 

 


 

 



 

 
Banking
Commercial
Educational
Entertainment
Healthcare
Industrial
Marine
Municipal
Parking Structures
Recreational
Religious
Wind Energy