| |
|
Oswego Grande Park Jr. High School Site
26923 West Grande Park BLVD
Plainfield, IL. 60544
Superintendent: Joe Berry
Updated on: 6-12-08 .
- Carpets are being installed
- Final flooring is being completed
- Finishing trims for all mechanical trades
- Mill work is being finished
- Total job site is 95% complete
- Ceilings, flooring and final painting are being completed
- Landscaping is 50%
|
|

Archived Images:
5-1-08
2-13-08
11-26-07
5-30-07
7-22-07
|
|
|

Archived Images:
5-1-08
2-13-08
1-09-08
11-20-07
9-06-07
9-11-07
|
|
Ogden Professional
Superintendent: Rob Cinto
Updated on: 6-12-08
- Third and second floors have been poured.
- All floors have been poured.
- 80% glass is in
- All rough plumbing, electric and rough HVAC is in.
- Tremco Roofing is complete.
- Arched upper & lower canopy roofs are rough framed. They are being prepared for composite panel system.
- All floors are rough framed.
- 3rd floor is dry walled.
- 2nd floor dry wall started on site
- Exterior precast is painted.
- Monumental exterior sign has been poured.
- Final grading has begun.
- Final sidewalks and curbs are prepared for concrete.
|
|
New Aurora Police Station
Aurora, Illinois
Superintendent: Dan Peterson
Project Manager: Bill Arnolde
Updated on: 6-26-08
TAS Building:
- ½ of the Metal Decking for the roof is complete
- Precast panels are complete
- Steel erection detailing in progress, approximately 75% complete
- Electric Overhead Rough-in is going in
- Electrical & Storage area floors are pored.
______________________________________
Parking Garage:
- Foundations are complete for parking garage
|
|

Archived Images:
6-26-08/2
6-26-08
6-20-08/2
6-20-08
5-13-08
5-13-08/1
5-13precast-2
5-13precast-1
2-15-08
9-6-07 |
|
|

Archived Images:
5-1-08
2-13-08
7-20-07
6-13-07
|
|
KVR
Aurora, Illinois
Superintendent: Tim Werrline
Updated on: 6-12-08
- Future patio areas and matching sidewalks are completed
- Final painting is being completed on site
- Roofers are installing the slate shingles. Process is about 90% complete
- Future patio areas and matching sidewalks are completed
- Brickwork on building is complete
- Main power is hooked up
- Glazing is 98% complete
- Window frames and glass are installed.
- “EIFS” is being installed on site. (A textured wall that looks similar to stucco) Process is about 90% complete
|
|
Greene Field Park
Superintendent: Mike Testa
Updated on: 6-26-08
Project Status: Complete
- Buildings are finished on site.
- Playground is erected.
- Fence and dugout are in place.
- Seating and baseball fields are complete
|
|

Archived Images:
5-1-08
4-07-08
4-04-08
11-26-07
|
|
|
|
|

Archived Images:
6-12-08
5-13-08
5-1-08
|
|
The Tillers Health Care Residence
Oswego, Illinois
Superintendent: Gary Ellingwood
Updated on: 6-12-08
- Glass is all in
- South Door is being installed
- All other doors are in
- Dirt/Grading is started in preparation for exterior concrete
- Drywall is finished
- Cabinets are being installed
- Smokes and fire alarms are in
- Duct work is finished
|
|
FVPD Blackberry Farms Silo Repair
Updated on: 5-13-08
- The Silo at the Fox Valley Park District’s Blackberry Farms was starting to lean because of rotting at the base from age.
- R.C. Wegman shored the bottom of the silo, jacked it up and cut out the rotted wood.
- It was replaced with a masonry base.
|
|

|
|
| |
|