Valley Electric has been finishing up ceiling trim including grid lighting. Sherman Mechanical has diffusers installed in the grid. Just Rite Acoustics will begin putting ceiling tiles in later this week. Valley Fire has sprinkler heads trimmed out. Brookdale Decorating has been busy painting and cleaning exposed concrete. The next step is to finish any remaining above ceiling work and place ceiling tiles so Flooring can be installed with Corporate Concepts following behind with wall track.