Fermilab 13th Floor Renovation Progress

Fermilab 13th Floor Renovation Progress

Rough-in work is moving along at Fermilab 13th Floor Renovation. Sherman Mechanical has been running ductwork and Valley Electric is installing cable tray and conduit. Valley Fire Protection is also on site swapping out sprinkler heads. The next phase after rough-in will be installing ceiling grid. Stay tuned for more updates on the 13th floor renovation progress.

No Comments