Field Status

Valley Electric has been finishing up ceiling trim including grid lighting. Sherman Mechanical has diffusers installed in the grid. Just Rite Acoustics will begin putting ceiling tiles in later this week. Valley Fire has sprinkler heads trimmed out. Brookdale Decorating has been busy painting and...

Blackhawk Park is built on the site where the original West Aurora High School stood since 1905. The sites historical significance played an influential role in its planning and development as did Park District residents who helped shape concept plans through open house forums last...

Blackhawk park is just a few weeks away from the grand opening! Save the Date: October 18, 2017 at 4 p.m.  The park is really shaping up to be a magical place! The trees have been planted, sod is rolled out and the shelter roof...

The track at the new East Aurora High School football and track stadium is almost complete. The track is new Spurtan, BV material, which is a two-layer sandwich style polyurethane track system. Stay tuned for final images of the track including the lane striping and...