Drywall and painting along with the ceiling grid will be complete on all floors by mid March. The HVAC contractor and electricians have been working right behind the grid installers putting in registers and lights. Doors and hardware are in progress as well as installing...

The warehouse is complete and final inspection has taken place and passed. All 128 - 10' sky light sections have been installed and what a difference they make with the lights off, the new warehouse addition only has 3 emergency lights on throughout the day because...